Infineon receives constructing allow for closing development part of Good Energy Fab in Dresden


– Saxony’s Prime Minister Michael Kretschmer palms during the last excellent
constructing allow for the development mission
– Infineon is on schedule with the Good Energy Fab with the beginning of manufacturing
deliberate for 2026
– Complete funding of 5 billion euros in a state-of-the-art semiconductor
manufacturing in Germany
– With the fab, Infineon is rising provide chain safety in Europe and making a
important contribution to decarbonization and digitization

Infineon Applied sciences AG is on schedule with the development of the Good Energy Fab in Dresden and is initiating the ultimate development part. Throughout a go to, the Prime Minister of the Free State of Saxony, Michael Kretschmer, formally handed during the last excellent constructing allow for the brand new fab issued by the State Directorate of Saxony. The excavation of the constructing pit has now been accomplished. The shell and constructing development are at the moment progressing on the concrete basis, which is as much as two meters thick. Infineon formally broke floor for the brand new plant in Dresden in Might 2023. Manufacturing is scheduled to begin in 2026. The manufacturing will give attention to semiconductors that promote decarbonization and digitalization.

With a complete funding of 5 billion euros, the corporate is making a major contribution to the European Fee aim to extend the EU’s share of world semiconductor manufacturing to twenty % by 2030. The semiconductors manufactured in Dresden will safe future worth chains in key European industries. The merchandise manufactured within the new manufacturing facility shall be used within the automotive and renewable power industries. The interplay of energy semiconductors and analog/mixed-signal parts permits notably energy-efficient and clever system options – therefore the identify Good Energy Fab.

“The development of the Good Energy Fab is a giant win for Dresden, Saxony, Germany and Europe,” says Michael Kretschmer, Prime Minister of the Free State of Saxony. “Infineon’s fourth manufacturing module in Dresden is one other vital constructing block in strengthening Europe’s resilience within the area of microelectronics. It’s a additional step in the direction of reaching the European Fee’s aim of accelerating Europe’s share of world chip manufacturing to twenty %. Because of a considerate cooperation between the corporate, the Free State of Bavaria, the native authorities, and the federal authorities, it has been doable to get the funding off the bottom and to difficulty the related permits rapidly. In consequence, the semiconductors that we urgently want for the mobility and power transition could be produced within the new fab beginning in 2026.”

“We’re making glorious progress with the development of our state-of-the-art Good Energy Fab in Dresden. We’re proper on schedule additionally due to the superb cooperation with the authorities,” says Dr. Rutger Wijburg, Member of the Administration Board and Chief Operations Officer of Infineon. “With our strategic determination to proceed investing in Dresden, we’re securing the long-term way forward for the positioning and strengthening the manufacturing base for semiconductors in Europe.”

The scale of the development web site are spectacular. On common, development staff have eliminated round 8,000 tons of soil on daily basis because the begin of labor. A complete of 450,000 cubic meters of excavated soil has been produced, which corresponds to the amount of 180 Olympic swimming swimming pools. The soil is being briefly saved in a specifically ready space close to the Dresden Airport freeway junction. The 22-metre-deep pit not solely compensates for the pure gradient, but in addition supplies a agency basis for the 150- to 190-centimetre-thick base plate, which is meant to cut back vibrations – from passing streetcars, for instance – to a minimal. Even minimal vibrations can have an effect on the delicate semiconductor manufacturing.

Within the subsequent development part, the basement ranges shall be constructed, together with different ranges. The clear room – the guts of the Good Energy Fab – is deliberate for the fourth degree. As soon as accomplished, will probably be at the very same top as the positioning’s three current manufacturing rooms. It will optimize an built-in manufacturing. The longer term development part of the mission features a complete of ten tower cranes, a few of them 80 meters excessive to assist as much as 1,200 development staff who shall be engaged on the positioning on daily basis in a number of shifts.

The funding in Dresden is a part of the corporate’s technique to succeed in CO2-neutrality by 2030. The Good Energy Fab units new effectivity requirements for the consumption of vital assets akin to power and water. This has a constructive impression on the carbon footprint of Infineon. Even right this moment, Infineon’s merchandise, that are utilized in photo voltaic and wind energy crops, scale back 34 instances the quantity of CO2 emitted throughout their manufacturing over their lifetime.

With the funding within the new plant, Infineon is creating an extra 1,000 jobs within the Saxon state capital. The corporate at the moment employs roughly 3,250 folks in Dresden. The variety of trainees has already been considerably elevated with the brand new Fab. Topic to the European Fee’s state support determination and the nationwide grant process, the mission is to be funded in accordance with the goals of the European Chips Act. Infineon is aiming for public funding of round one billion euros.